Selectivity means that in the event of a malfunction, only the nearest higher-level device will power on. This serves as a preliminary check. upper/lower rated current ratio ≈ 1.6 and above It shows the possibility of selectivity in the overload region; Short circuit selectivity is only possible with manufacturer coordination tables. It is verified.

Overload pre-check: In(upper) / In(lower) ≥ ~1.6
Example calculation: Upper 100 A, lower 40 A → ratio 2.5 ≥ 1.6 → selectivity possible under overload; short-circuit selectivity should be verified with the manufacturer's table.

Selectivity / Coordination Pre-Check

Preliminarily assess the possibility of selectivity based on the rated current ratio of the upper and lower protective devices.

Rated current ratio
Notes: This is a preliminary check. The general practical ratio for selectivity in the overload region is ≈ 1.6; Short-circuit selectivity can only be verified using manufacturer selectivity (coordination) tables and tripping curves. Full selectivity can be achieved with current limiting, time-phasing, or zone-selective interlocking (ZSI).

How is it calculated?

  1. Enter the rated current (A) of the upper (feeding) device.
  2. Enter the rated current (A) of the lower (powered) device.
  3. Press Check; the ratio and selectivity assessment will be displayed.

Frequently Asked Questions

What is selectivity?
In the event of a malfunction, only the protective device closest to the fault will trip, leaving the higher levels energized; this is crucial for continuity.
How is selectivity achieved?
Rated current tiering, time delay, current limiting, or zone selective interlocking (ZSI) are used; precise verification is performed with manufacturer selectivity tables.
Does this tool guarantee complete selectivity?
No, it's only a preliminary indication for the overload region; short-circuit selectivity must be verified with tripping curves and manufacturer's tables.

Related tools and services

This tool and its content are for general informational purposes only; they do not constitute a binding inspection/declaration of conformity. Definitive results will be determined through on-site inspection in accordance with relevant legislation and standards. Get a quote →