Two parameters are decisive in selecting a residual current device (RCD): threshold (IΔn) And medicine. Additional protection for sockets and personnel is IΔn ≤ 30 mA, and for fire protection it is typically 300 mA. The type is selected according to the type of leakage current produced by the load (AC/A/B).

Additional protection (sockets): IΔn ≤ 30 mA · Fire protection: ~300 mA
Example calculation: Power strip circuit + electronic load (SMPS/LED) → 30 mA (personnel/additional protection) and Type A are recommended.

Selecting a Residual Current Device (RCD)

View the recommended leakage current threshold (IΔn) and relay type according to the intended use and load type.

Leakage current threshold IΔn
Relay type
Notes: According to IEC/HD 60364-4-41, for sockets and personnel protection. Additional protection IΔn ≤ 30 mA Recommended; typical 300 mA for fire protection. Type selection depends on the type of leakage current produced by the load: AC (sinusoidal), A (pulsed DC component — electronic), B (straight DC component — inverter), EV charging with Type A + 6 mA DC sensing or Type B. The final choice is determined by the installation conditions.

How is it calculated?

  1. Select the intended use (power outlet, wet area, fire protection, etc.).
  2. Select the load/circuit type (classic, electronic, inverter, EV charger).
  3. Press Suggest; the threshold and relay type will be displayed.

Frequently Asked Questions

Should I choose 30 mA or 300 mA?
30 mA for sockets and personnel protection (additional protection), typical 300 mA for main fire protection.
What is the difference between Type A and Type AC?
Type AC only detects sinusoidal AC leakage current; Type A also detects electronic loads containing pulsed DC components.
What RCD is needed for an EV charging station?
Due to the risk of straight-line DC leakage, either Type A + 6 mA DC detection or Type B is used.